Snoqualmie Tribe Ancestral Forest | The Snoqualmie Tribe owns a 12,000 acre block of forest land situated on the western slopes of the Cascade Mountains between the Mt. Baker Snoqualmie Forest to the east, other privately owned forestland to the west, the Seattle Public Utilities North Fork Tolt Reservoir to the south, and forestland abutting WA State Hwy 2 to the north. The Ancestral Forest property lies in Township 26 N Range 9 E. Primary vehicle access to the Ancestral Forest is from Hwy 2 near the town of Index, WA. The property address is Forest Service Rd 62, Index, WA 98526

Need for Services | The Snoqualmie Indian Tribe requires professional engineering, environmental, and construction services to support the repair and restoration of roadways within the Snoqualmie Tribe Ancestral Forest that were damaged during the FEMA‑declared disaster event FEMA‑DR‑4906‑WA.

Severe storms, flooding, landslides, and related soil instability have compromised multiple forest road segments essential for Tribal land stewardship, cultural access, natural resource management, and emergency response. These damaged roads represent critical infrastructure that must be restored to safe, reliable, and environmentally compliant conditions.

Engineering evaluation, design, permitting, environmental analysis, and construction services are needed to ensure that all repairs incorporate appropriate mitigation measures, strengthen long-term resilience, and protect sensitive cultural and ecological resources within the Ancestral Forest. These services are essential to restore access, prevent further degradation, and secure federal reimbursement under the Public Assistance Program.

Scope of work | The Snoqualmie Indian Tribe seeks qualified Contractors with experience in forested mountain terrain in the cascades to provide design‑build services to restore damaged roads, drainage systems, and slope‑stability features in the Snoqualmie Tribe Ancestral Forest (STAF) resulting from FEMA Disaster DR‑4906‑WA.

The selected contractor will support the Tribe in developing and executing the scope of work necessary to achieve permanent road repairs in alignment with FEMA Category C (Roads and Bridges) guidelines. The work must meet FEMA Public Assistance requirements, including technical documentation, environmental/historic preservation compliance, and adherence to federal, state, and Tribal standards.

Work must restore facilities to pre‑disaster condition and may incorporate appropriate measures to strengthen long-term resilience is mitigation measures are FEMA-eligible.

The Contractor shall provide all labor, materials, equipment, engineering, environmental protection measures, construction activities, FEMA PA documentation, and project management necessary to complete the work. The Contractor is responsible for any additional analyses or tasks required to meet FEMA eligibility, Tribal standards, and applicable codes.

All design and construction must meet or exceed pre‑disaster quality and structural capacity. Required engineering includes full surveys, mapping, drainage evaluations, culvert assessments, geotechnical review, and hydrologic/hydraulic analysis. Substitutions require written Tribal approval.

All work must follow Tribal environmental and cultural protection protocols and be coordinated with Tribal Environmental, Cultural Resources, and Forestry staff. Tribal monitors may be assigned for oversight of earth movement.

Construction shall follow approved plans. Field staking and design verification require Tribal approval. Non‑compliant work must be corrected at the Contractor’s expense.

The Contractor must maintain complete FEMA‑compliant documentation, including daily logs, load tickets, quantity tracking, photos, GPS‑based records, as‑builts, and engineering certifications. Payment may be withheld if documentation is incomplete.

Schedules shall account for forest conditions and seasonal limitations. Deviations over five days require written justification and Tribal approval. Work outside FEMA‑approved or Tribal‑approved scope is not eligible for reimbursement.

Submittal of Proposals | All correspondence shall be directed to Greg King, Geologist, Snoqualmie Tribe greg.king@snoqualmietribe.us or designee. Please submit RFPs by 5pm on Thursday, November 19, 2026. Late responses will not be accepted or considered.

Download the Full RFP in PDF Format